Visayas Base-Load Power Development Project

» Case registry

April 2012

On 11 April 2012, the ADB Board of Directors approves the CRP recommendations on the compliance review of the Project. 

On 2 April 2012, ADB Board of Directors considered the CRP Final Report and its recommendations.

March 2012

On 12 March 2012, CRP submits to the ADB Board of Directors its Final Report with recommendations for Board's consideration.  The Board is scheduled to discuss and consider the report on 2 April 2012.

February 2012

Requesters and Management responses to the CRP Draft Report were received on 20 and 23 February 2012.

January 2012

The CRP issued its Draft Report to ADB Management and the Requesters of compliance review on 20 January 2012. Management and Requesters have 30 days to review the Report and provide their comments to CRP.

September 2011

The CRP visited the project site in Naga, Cebu on 15-16 September 2011 and held discussions with officials and staff of the project sponsor as well as with the requesters, nongovernment organizations, and affected people. The Panel also visited Naalad and Pangdan where the excavated ash from the project site had been used for landfilling, and the proposed ash disposal site in Balili.